As we enter the final stretch of 2025, construction continues to progress steadily across the early stages of our community, with significant progress made throughout Stages 1 and 2 this month.
In Stage 1A, electrical reticulation is on track to be completed this week. Opticomm and gas will also be installed during this time. Water and stormwater works are now complete, as are all road crossings, with kerbs, footpaths and roof water pipe works getting underway.
In Stage 1B, road crossings are under construction, marking another step forward in the delivery of this stage. Drains and conduits will commence next week.
And finally, in Stages 2A and 2B, electrical reticulation will be occurring over the month, with kerb installation to follow. Water and stormwater infrastructure is complete, with road crossings underway.
These works form an important part of building the foundations for the future Amory community, as we look forward to sharing more milestones in the months ahead.