Construction is continuing steadily across the early stages of Amory, with significant progress made throughout Stages 1 and 2 this month.
Along the Link Road, electrical and gas trenching has now been completed, ensuring essential services are in place to support future development.
In Stages 1A and 1B, retaining wall construction is ongoing, while in Stage 1B, the team has completed sewer installation and is continuing with stormwater works. Over in Stage 1A, crews are now commencing subgrade preparation, marking another step forward in the delivery of this stage.
These works form an important part of building the foundations for the future Amory community, as we look forward to sharing more milestones in the months ahead.